November 18

Construction report: Residential block «Kyivskyi»

Dear site visitors!

We inform you about the progress of construction of the residential complex "Kyivskiy".
As of 18.11.2019 the following volume of works has been completed:

In the second launching complex of the 1st stage of the Kyivskiy residential complex
• work on the facade of the house is being continued;
• we carry out plastering of walls of commercial premises;
• arrange insulation and screed on terraces;
• We perform installation of metal structures of commercial premises for advertising.
Finishing the walls and partitions of the 6th floor of the second turn
In the third launching complex of the 4th turn:
• the formwork is made and the frame of the reinforced concrete belt is made;
• horizontal waterproofing of the foundation walls is carried out.

Let's move on!
Your New Home Company Group